QUARTERLY CONSTRUCTION UPDATES

Photo GalleryConstruction Updates

September 2025

  • Concrete poured levels 1-4
  • MEP trades fully mobilized on site and are working up the podium
  • Temporary power completed
  • Unit coordination is complete; Juneau is releasing materials on time and on schedule

April 2025

  • Completion of deep foundation piles, including demobilization of pile contractor.
  • Mobilization of concrete shell contractor.
  • Erection of north and south tower cranes.
  • Foundation excavations, pile chipping, rebar tying, concrete placement, and waterproofing of foundations.
  • Site backfilling up to level 1 floor elevation after foundation concrete placement.
  • Level 1 to 1.5 vertical concrete placement, columns and walls.
  • Initial underground plumbing and electrical coordination and installation.
  • Start of elevated deck formwork construction.

December 2024

  • Deep foundation system installation. 662 85′ deep cast in place concrete piles.
  • Installation of underground primary electrical utility service.

October 2024