QUARTERLY CONSTRUCTION UPDATES

Photo GalleryConstruction Updates

February 2026

  • Currently on Level 19: Structural work has advanced to Level 19, with crews actively progressing upward and maintaining schedule milestones.
  • Windows continue through Level 8: Window installation is ongoing through Level 8, providing enclosure and weather protection on lower floors.
  • Layout in progress: Interior layout activities are underway, including unit demising, corridor layouts, and coordination with MEP trades.
  • Framing on Level 5 and 6: Interior framing is actively progressing on Level 5 and 6, with crews installing partitions and allowing for rough-in to progress.
  • Masonry continues: Masonry work is ongoing across designated elevations
  • Mechanical, Electrical, and Plumbing rough-in ongoing: MEP rough-in activities are in progress throughout multiple levels, coordinated with framing and layout work.
  • Slab on grade continues: Townhome slab-on-grade concrete has been successfully poured, Parking garage slabs continue

November 2025

  • Concrete poured levels 1-7
  • Temporary power completed
  • MEP trades fully mobilized on site and are working up the podium
  • Unit coordination is complete, and Juneau is releasing materials on time and on schedule
  • Underground storm and sanitary in progress
  • Hoist installation scheduled for November
  • Mobilizing Masonsub in 3 weeks
  • Mobilizing framing in 5 weeks
  • Masonry mobilized

September 2025

  • Concrete poured levels 1-4
  • MEP trades fully mobilized on site and are working up the podium
  • Temporary power completed
  • Unit coordination is complete; Juneau is releasing materials on time and on schedule

April 2025

  • Completion of deep foundation piles, including demobilization of pile contractor.
  • Mobilization of concrete shell contractor.
  • Erection of north and south tower cranes.
  • Foundation excavations, pile chipping, rebar tying, concrete placement, and waterproofing of foundations.
  • Site backfilling up to level 1 floor elevation after foundation concrete placement.
  • Level 1 to 1.5 vertical concrete placement, columns and walls.
  • Initial underground plumbing and electrical coordination and installation.
  • Start of elevated deck formwork construction.

December 2024

  • Deep foundation system installation. 662 85′ deep cast in place concrete piles.
  • Installation of underground primary electrical utility service.

October 2024